Single leaf Bascule Bridge, Canary Wharf, London

Upper Bank Street Bridge

The construction of the Canary Wharf Crossrail Metro Station (‘Elizabeth Line Station’) considerably narrowed the adjacent North Dock channel. The Upper Bank Street Lifting Bridge replaced an existing, longer bridge over the North Dock, and formed part of the prestigious Crossrail Project.

What work was done by Qualter Hall on the Upper Bank Street Lifting Bridge?

Qualter Hall was contracted by Hollandia for Canary Wharf Contractors (Crossrail) Ltd (CWC). Our scope of works included for the design, procurement, manufacture, assembly, delivery, installation and commissioning of electrical and hydraulic equipment including the following:-

Commissioning was carried out in a densely populated and built-up environment which was part of one of Europe’s largest construction sites at the time.

The Upper Bank Street (UBS) Lifting Bridge weighs 275 tons and spans 26 meters, carrying traffic over the North Dock. It is situated at the north end of Canary Wharf, linking Upper Bank Street with the Crossrail (‘Elizabeth Line’) Station. The north side of the bridge deck is lifted using a hydraulically powered lifting cylinder which was reused from the previous bridge. When the bridge is lifted, the North Dock is navigable for shipping traffic in compliance with the British Waterways requirement.